Finish setting up your account — 60% complete
Sunday, November 1, 2026
Active Projects
11
Completed Projects
4
Total Backlog
$330.6M
Billed YTD
$37.5M
Open CO Value
$0K
Open Warranties
0
Open RFIs
4
Overdue Tasks
0
Total Users
50
Manpower (last 14 days)

No manpower data yet — crew counts come from Site Diary entries.

Safety — TRIR
0.00
Total Recordable Incident Rate (YTD)
This month: 0.00 Recordables: 0
TRIR = (Recordables × 200,000) / Hours worked. Log safety incidents and timesheet hours to populate.
Active Projects View All
ProjectPMBudget BilledCOsRFIsDefs
Atlanta Fulfillment Center Active
Atlanta Logistics Partners LLC
James Fleury $121,221K
0%
— 0 0
Atlanta Fulfillment Center Active Bidding
Atlanta Logistics Partners LLC
James Fleury $121,221K
0%
— 0 0
Granite Ridge Commerce Center — TEST Active Construction
Granite Ridge Industrial Partners LLC
Project Manager $28,750K
0%
— 0 0
MTM Community Distribution Centre — Montréal, QC Active
Mafeu Tchaleu Marie Foundation
James Fleury $44,700K
0%
— 0 0
Riverbend Transit Maintenance Facility — TEST Active Construction
Riverbend Transit Authority
Project Manager $14,750K
0%
— 0 0
Zack Building 2 Active
The Harborline Supply, Inc.
Sr PM $0K
0%
— 0 0
Atlanta Fulfillment Center Pre construction
The Harborline Supply, Inc.
— $0K
0%
— 0 0
rakesh demo Design build project Pre construction
Hillcrest Hospice LLC
Project Manager $0K
0%
— 0 0
Riverside MOB Phase 1
Riverside Medical Center
James Fleury $297K
0%
— 0 0
Test Project Big Draft Bidding
Mafeu Tchaleu Marie Foundation
James Fleury $0K
0%
— 0 0
Zack Building 2 Draft Bidding
Rajesh Constructions
Sr PM $100,000K
0%
— 0 0
Completed Projects 4 View All
ProjectPMClientBudgetEnd Date
Lakeview Health Medical Office Building — Alpharetta, GA — — $28,960K Sep 30, 2025
Harborline Supply RDC — Conyers, GA Project Manager The Harborline Supply, Inc. $121,221K Sep 15, 2025
Hillcrest Hospice — Conyers, GA — Hillcrest Hospice LLC $3,200K Mar 31, 2025
Vantage Grocers Distribution Center — Savannah, GA — — $89,700K Aug 30, 2024
Project Health Summary All Projects
Project Open RFIs Open COs Deficiencies Budget Used Health
Atlanta Fulfillment Center
Atlanta Logistics Partners LLC
0 — 0
0%
On Track
Atlanta Fulfillment Center
Atlanta Logistics Partners LLC
0 — 0
0%
On Track
Granite Ridge Commerce Center — TEST
Granite Ridge Industrial Partners LLC
0 — 0
0%
On Track
MTM Community Distribution Centre — Montréal, QC
Mafeu Tchaleu Marie Foundation
0 — 0
0%
On Track
Riverbend Transit Maintenance Facility — TEST
Riverbend Transit Authority
0 — 0
0%
On Track
Zack Building 2
The Harborline Supply, Inc.
0 — 0
0%
On Track
Atlanta Fulfillment Center
The Harborline Supply, Inc.
0 — 0
0%
On Track
rakesh demo Design build project
Hillcrest Hospice LLC
0 — 0
0%
On Track
Riverside MOB Phase 1
Riverside Medical Center
0 — 0
0%
On Track
Test Project Big
Mafeu Tchaleu Marie Foundation
0 — 0
0%
On Track
Recent Activity View All
  • File uploaded: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 15, 12:07 am
  • File deleted: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 15, 12:07 am
  • File deleted: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 15, 12:07 am
  • File uploaded: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 14, 11:59 pm
  • File uploaded: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 14, 11:58 pm
  • File deleted: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 14, 11:58 pm
  • File uploaded: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 14, 11:52 pm
  • File deleted: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 14, 11:52 pm
  • File uploaded: 2025.01.06_Current RACS.pdf
    James Fleury · Jul 14, 11:51 pm
Monthly Billings — 2026
My Action Items View All
Loading action items…
0
WORKERS ON SITE
0
OPEN PUNCH ITEMS
0
INCIDENTS THIS WEEK
0
MILESTONES DUE SOON
Open Punch Items View All
  • All clear!
Upcoming Milestones
  • No upcoming milestones.